AVERAGE
QUALITY MATERIALS AND WORKMANSHIP
BASE
SPECIFICATIONS
1)
Roof: |
Gambrel,
Average Quality Roofing,
1' Rigid Insulation |
5)
Floors: |
None |
2)
Foundation: |
Treated
Poles |
6)
Plumbing: |
None |
3)
Exterior Walls: |
Steel,
Two (2) Sliding Doors
One (1) Entry Door |
7)
Lighting: |
None |
4) Interior
Finish: |
None |
8) Other
Items: |
None |
BASE
COST PER S/F
SIDEWALL
HT. |
2500 |
5000 |
7500 |
10000 |
15000 |
20000 |
10'
|
10.90 |
10.04 |
9.47 |
9.63 |
9.45 |
9.17 |
14'
|
12.26 |
11.20 |
10.59 |
10.62 |
10.40
|
10.08 |
For
Low Quality, multiply by .75 |
For
High Quality, multiply by 1.25 |
NOTES:
Depreciation: For High Quality - Table D-III, Average Quality - Table D-II,
Low Quality Table D-I
Cost Conversion Factors: See F-2
Adjustments To Base Specifications - See Agriculture Adjustments Section
|