For Current Technical Proposals


E-mail question(s) to the attention: Manager of Professional Services, Procurement. Specify "TP # 117 question" in subject line.

Questions will be accepted up to question cut-off date noted in the technical proposal.

Technical Proposal


TP-117


Question 1: May we substitute a BSCE with 15 years of traffic signal and highway lighting design experience for the required BSEE, in the Electrical Engineering – Signals/Lighting Task Leader role?

Answer 1: It’s a business decision of your firm to propose the individual who best fits the qualifications for the Project Manager and/or Key Staff team leader. Specific education and experience substitution questions for Project Manager and Key Staff positions cannot be addressed during the solicitation process, because each project is different, the solicitation provides the stated requirements, and if an answer were supplied it could inadvertently be considered as receiving a “pre-score” for the position before the closing date of the technical proposal submission.

Question 2: Typical NJDOT EOI always stats that “Technical proposals are being solicited for Preliminary Engineering, Final Design and Construction Engineering Services. However, services under the original agreement shall be limited to the completion of Preliminary Engineering services. Final Design Services and Construction Engineering Services may be initiated at a later date as a CONSULTANT AGREEMENT ADDENDUM, at the sole discretion of the State”. Please clarify that this Technical proposals are being solicited for the Preliminary Engineering phase of the project ONLY. Will a separate posting be required for Final Design?

Answer 2: The solicitation should say, "Technical proposals are being solicited for Preliminary Engineering, Final Design and Construction Engineering Services. However, services under the original agreement shall be limited to the completion of Preliminary Engineering services. Final Design Services and Construction Engineering Services may be initiated at a later date as a CONSULTANT AGREEMENT ADDENDUM, at the sole discretion of the State." A revised file has been posted.


Question 3:
Are the Team Leaders for Bridge Design – Movable, Mechanical Engineering – Movable, and Electrical Engineering – Movable required to be Professional Engineers in New Jersey or licensed in any state?


Answer 3:
A PE will be accepted from any State for these team leaders.

 

Question 4: Will the Department allow 11x17 sheets for the 2 graphics as opposed to 8.5x11?

 

Answer 4: Yes.

 
Go to NJDOT home page Contact Us | Privacy Notice | Legal Statement | Accessibility Statement  Go to State of New Jersey home page
  department: home | about | NJ commuter | in the works | business | engineering | freight, air & water | capital | community | data | links | index
  statewide: NJ Home | about NJ | business | government | state services A to Z | departments

  Copyright © State of New Jersey, 2002-2020
  Department of Transportation
  P.O. Box 600
  Trenton, NJ 08625-0600
OPRA - open public records act

  Last Updated:  July 29, 2016