Concept Development
Executive Summary
The Concept Development (CD) Phase
may begin with a Problem
Statement (Form TP-1) approved
by the Capital Program Committee
(CPC) and provided to the
Division of Project Management
(DPM). The
Problem Statement may be
validated, redefined, or
in some cases invalidated,
and in which case, the project
may not advance further.
The CD Phase involves drafting
a well-defined and well-justified
Purpose and Need Statement
focusing on the primary transportation
need to be addressed. CD
Phase elements include, but
are not limited to, data
collection, coordination
with New Jersey Department
of Transportation (NJDOT)
Subject Matter Experts/local
stakeholders, development
of a reasonable number of sensible
and practical conceptual alternatives
and investigation of all
aspects of a project. These
aspects may include environmental,
right of way, access, utilities,
design, community involvement,
and constructability.
Note: Studies meeting the requirements
of Limited Scope will include
a subset of the CD Phase
elements listed above.
Data collection may include, but
is not limited to NJDOT management
systems data (e.g., Safety
Management System, Bridge
Management System, etc.),
traffic/crash data, “as-built” plans,
environmental screening,
review of any concurrent/adjacent
projects and other relevant
data that would or would
not substantiate the project
need. Collected data is analyzed
and compared to established
criteria and standards. Deviations
from or deficiencies with
criteria are documented and
serve as a base for alternatives
development.
During the CD Phase,
DPM initiates or continues
the coordination with internal/external
stakeholders, who through
their technical expertise
or local knowledge of the
project area/problem, help analyze
and interpret the collected data
that can help to clarify the project
needs.
A primary task of stakeholders,
is to develop “conceptual
alternatives” in line with
their requirements/guidelines
and ranking criteria. Stakeholders
are also responsible for
identifying possible fatal
flaws and selecting the Preliminary
Preferred Alternative (PPA)
based on the Purpose and
Need Statement. These alternatives
and the PPA are analyzed
based on the impacts to right
of way, the environment,
utilities, and the community.
Generally, survey/mapping will
not be performed during CD,
but will be included under
the Preliminary Engineering (PE)
Phase.
Objective(s)
The major objectives of the CD
Phase are to identify and
compare reasonable alternatives
and strategies that address the
Purpose and Need Statement and
select a PPA.
The CD Phase will provide
the information to determine
whether or not the study
can be advanced to the next
phase of the Project Delivery
Process and to procure a designer
to take the potential project
through PE, Final Design (FD) and
Construction (CON). The CD Phase
provides the framework for advancing
the project into the PE phase.
Funding
Funding for the CD Phase
is generally provided through
State Task Order Term Agreements
and may involve a federal funding
source.
Key Stakeholders
Coordination with Key Stakeholders
is as critical in the CD
Phase as it is in all other
phases. Key internal stakeholders
include NJDOT Subject Matter
Experts (SME). Key external
stakeholders include the affected
municipalities, counties and others
impacted by the project.
DPM conducts meetings with the
external stakeholders to
solicit input and brief the
officials on the project
status. It is essential to start
the discussion with the local officials
as early as possible in the CD
Phase. As the study advances, more
meetings should regularly take
place to update all the stakeholders
and keep them involved in
the development of conceptual alternatives.
Meetings with the internal stakeholders
or SMEs are called Scope Team/Core
Group Meetings. These meetings
will introduce the project to the
SMEs, obtain information from the
various SME groups and start to
address concerns from all disciplines.
Once the affected disciplines are
identified, a Core Group will be
formed and members will hear concerns
from other disciplines and may
recognize that solving one problem
may adversely affect another. The
goal of the Core Group members
is to consider all input and reach
a consensus on the project scope
and the PPA.
Conducting scope team/core group meetings is a team effort. It is critical that all members thoroughly evaluate a project and participate in the CD process.
The following list includes, but is not limited to, possible stakeholders:
Internal Stakeholders (SME)
- Division of Project Management
- Division of Community
and Constituent Relations
- Bureau of Structural Engineering
- Bureau of Traffic and Signal Safety Engineering
- Bureau of Traffic Engineering and Investigations
- Bureau of Safety Programs
- Value Solutions Unit
- Value Engineering Unit
- Bureau of Quality Management
Services
- Office of Schedule and Budget
Management
- Bureau of Landscape Architecture
and Environmental Solutions
- Office of Stormwater/Stream Encroachment
- Division of Bridge Engineering
and Infrastructure Management
- Division of Highway and Traffic
Design
- Bureau of Access Design and
Right of Way (ROW) Engineering
- Office of Geotechnical Engineering
- Drainage and Pavement Management
- Regional Maintenance Operations
- Utility Management Unit
- Bureau of Regional Design and
Surveying Services
- Bureau of Traffic Operations
- Intelligent Transportation Systems (ITS)
- Office of Constructability Review
- Bureau of Commuter and Mobility
Strategies (Bicycle and
Pedestrian Unit)
External Stakeholders:
- Federal Highway Administration (FHWA)
- NJ Department of Environmental Protection
- State Historic Preservation
Office (SHPO)
- Metropolitan Planning Organization (MPO)
- NJ TRANSIT
- Meadowlands Commission
- Pinelands Commission
- Highlands Council
- D&R Canal Commission
- Delaware River Joint Toll Bridge Commission
- Other Authorities (NJ Turnpike Authority, South Jersey Transportation Authority, etc.)
- Delaware River Port Authority
- NJ Water Supply Authority
- US Coast Guard
- US Army Corps of Engineers
- National Weather Service, National Oceanic and Atmospheric Administration
- Business groups
- Utility companies
- Local Officials
- Elected Officials
- Affected residents
Phase Initiation
To initiate the CD Phase,
the following activities
should be completed:
- Problem Statement identification in the Study and Development Program (description, location, initial problem statement)
- Tier 2 Screening Report completion
- CPC approval to advance to CD
Major Tasks
The major tasks associated
with the CD Phase
are summarized below:
- Secure task order consultant
- Develop CD schedule and budget
- Identify potential funding source for Preliminary Engineering/Final Design/Construction
- Coordinate with the Environmental Team Leader to develop the CD Scope Statement
- Perform data collection: traffic/crash data, management systems, utility identification (letter #1), etc.
- Determine project type
- Develop a Project Management Plan
- Complete Environmental Screening. Initiate early coordination with SHPO, if appropriate
- Prepare Community Profile
- Prepare CD Public Involvement Action Plan (PIAP)
- Hold Core Group/FHWA
meeting: Identify NJDOT
SMEs (internal stakeholders
or scope team members),
coordinate and meet with
them to address the Purpose
and Need with respect to
safety, capacity, operational
improvements, environment
and community.
- Hold Local Officials
Meeting: Identify and meet
with local officials (external
stakeholders) to address
the Purpose and Need with
respect to safety, capacity,
operational improvements,
environment and community.
- Perform analysis of collected data, review data, prepare collision diagram, and other needed engineering analysis.
- Identify Substandard Design Elements
- Verify existing problem statement
- Complete CD Checklist
for Pavement Resurfacing
or Bridge Deck/Superstructure
Replacement (Limited Scope
Studies only)
- Perform Alternatives Development/Identify alternatives
- Evaluate conceptual alternatives
- Assess impacts to ROW, access, utilities and environment (Use Alternative Comparison Matrix)
- Identify fatal flaws and deficiencies
- Meet again with core group and local public officials to develop alternatives
- Identify environmental constraints
- Identify other project constraints
- Develop Conceptual Plans for Preliminary Preferred Alternative (PPA)
- Conduct constructability review of PPA (effort will vary depending on project)
- Confirm the environmental document that will be obtained in PE
- Develop Construction Cost Estimates of various alternatives
- Determine if design exception(s) may be needed and obtain reasonable assurance of approval
- Develop PE Scope Statement
- Prepare CD Report
- Obtain Resolution of Support document
Efforts to monitor and control
the project’s development
during the CD Phase
include:
- Establishing and updating the project’s Design Communications Report
- Providing project background
information, progress reports,
and important issues and
items in NJDOT’s
Project Reporting System
(PRS)
- Establishing, tracking and updating the project’s baseline schedule and budget
- Contract Management efforts, such as reviewing and approving project invoices and accompanying progress reports
- On-site Monitoring of Design Consultant to review project progress, status of budget, and quality of products
- Presenting project status at Department meetings, such as 60- to 90-Day Look Ahead Meetings and Pre-Advertisement Meetings
Products
The major products for the
CD Phase include:
- Clearly defined Purpose and Need Statement
- CD Report
- PE Project Management Plan
- Preliminary Preferred Alternative (PPA)
- Environmental Document Classification
- Reasonable Assurance of Design Exception Approval
- Preliminary Engineering Scope Statement to post for Consultant Selection to perform Preliminary Engineering/Final Design/Construction
- Design Communications Report (DCR)
- Systems Engineering Review Form (SERF) (If ITS devices are proposed)
Phase Closing
The following items must
be completed to leave the
CD Phase:
- Internal NJDOT Task Order Closeout activities
- Well-defined PE Scope
Statement
- Resolution of Support
- Purpose and Need Statement
- FHWA Approval of Concept Development Report
- Approval of PE Scope Statement
- Approval of Preliminary Preferred Alternative (PPA)
- Establishment of appropriate Environmental Document Classification
- Placement on Capital Program Screening Committee Agenda and recommendation to the CPC
- CPC Approval to initiate Preliminary Engineering
- Posting of Expression of Interest Solicitation for Technical Proposal (when FHWA accepts CD report and PPA)
- If needed, distribution of final CD report to identified internal/external groups
Some files are in Portable Document Format (PDF) and will need Adobe Acrobat Reader (available at our Adobe Access Page).
Flow Charts
Diagrams
Guidance Documents
Templates
|