I-295/I-76/Route 42 Direct Connection


Schedule

The following is the latest project schedule and is subject to funding and Right of Way availability.

Federal Highway Administration (FHWA) Review of Technical Environmental Study (TES) 2006
Pre-Draft Environmental Impact Statement (Pre-DEIS) and United States Army Corps of Engineers (UCACE) Conceptual Permit Application March 2007
Agency Review May 2007
Circulation of DEIS November 2007
Public Hearing January 2008
Final Environmental Impact Statement (FEIS) December 2008
Identify Preferred Alternative March 2008
Record of Decision March 2009
Preliminary Design August 2010
Final Design 2011 - 2017
Advanced Intelligent Transportation Systems (ITS) Contract Fall 2012 - Fall 2014
Construction Contract 1 Winter 2013 - Fall 2015
Construction Contract 2 Summer 2014 - Fall 2017
Construction Contract 3 Summer 2016 - Fall 2019
Construction Contract 4 Spring 2019 - Fall 2021

The actual project status is shown on Project Milestones (pdf 43k).

The file listed above is in Portable Document Format (PDF). You will need Adobe Acrobat Reader to view this file, which is available at our state Adobe Access page.

 
Go to NJDOT home page Contact Us | Privacy Notice | Legal Statement | Accessibility Statement  Go to State of New Jersey home page
  department: home | about | NJ commuter | in the works | business | engineering | freight, air & water | capital | community | data | links | index
  statewide: NJ Home | about NJ | business | government | state services A to Z | departments

  Copyright © State of New Jersey, 2002-2015
  Department of Transportation
  P.O. Box 600
  Trenton, NJ 08625-0600
OPRA - open public records act

  Last Updated:  June 4, 2014