Final Design and Construction

The New Manahawkin Bay Bridge Contract is currently under construction. Contract 3, the Rehabilitation of Existing Trestle Bridges (two trestle bridges over East Thorofare and West Thorofare) and Contract 5, the Environmental Mitigation Contract, began construction in February 2015. The remaining contracts are in the Final Design Phase. The purpose of this phase is to produce the project's construction contract documents for use in soliciting bids from prospective contractors and moving the project to the Construction Phase. Final Design includes the following major elements:

  • Continued advancement and completion of engineering design tasks initiated during the Preliminary Design Phase;
  • Project Contract Documents (Plans, Specifications, Construction Schedule and Construction Cost Estimate) to obtain bids from prospective contractors;
  • Environmental reevaluations, permits and clearanc es;
  • Executed utility relocation agreements;
  • Right of Way acquisition;
  • Access Design Agreements executed with property owners whose driveways are affected by the project;
  • Executed Jurisdictional Agreements with Stafford Township, Borough of Ship Bottom and Ocean County;
  • Continued community outreach.

Project schedule
Construction began on the first contract on May 3, 2013. The following schedule is planned at this time. Both funding and the types of proposed improvements will influence the later design and construction schedule.

Feasibility Assessment Phase Completed in 2007
Environmental Document approval Completed in September 2011
Design Phase(s) End of 2017
Construction Phase(s) 2013 - 2020

Construction
Bids were received on March 7, 2013 for the New Manahawkin Bay Bridge Contract. Thhis contract was awarded on April 24, 2013 and construction activities began on May 3, 2013. This contract includes building a new high level structure parallel to the existing Manahawkin Bay Bridge, along with various associated improvements to the bridge approaches and surrounding area.

Bids were received on November 6, 2014 for the Environmental Mitigation Contract. This contract was awarded on December 15, 2014 and construction activities began in February 2015.

Bids were received on November 13, 2014 for the Rehabilitation of Existing Trestle Bridges Contract. This contract was awarded on December 23, 2014 and construction activities began in February 2015.

nighttime photo
This is a nighttime view of the existing Manahawkin Bay Bridge.

 
Go to NJDOT home page Contact Us | Privacy Notice | Legal Statement | Accessibility Statement  Go to State of New Jersey home page
  department: home | about | NJ commuter | in the works | business | engineering | freight, air & water | capital | community | data | links | index
  statewide: NJ Home | about NJ | business | government | state services A to Z | departments

  Copyright © State of New Jersey, 2002-2015
  Department of Transportation
  P.O. Box 600
  Trenton, NJ 08625-0600
OPRA - open public records act

  Last Updated:  February 26, 2015