DECEMBER AWARDS
| OPS NO. |
PROJECT DESCRIPTION |
CONSULTANT |
AMOUNT |
| P3191 |
Supervision of Construction Services for Contract No.P100.024, Underground Storage Tank Upgrade/Removal at Various GSP Facilities |
Hatch Mott MacDonald |
$330,000.00 |
| P3137 |
Supervision of Construction Services for Contract No. P300.043, Improvements to GSP Interchange 67 |
Stone & Webster, Inc. |
$2,150,000.00 |
| T3167 |
Supervision of Construction Services for Contract No. T300.064, Ramp NWC Improvements at Interchange 18W, Roadway Widening, Grading, Paving and Structures |
The RBA Group |
$1,042,600.00 |
| P3175 |
Preliminary Design & Environmental Permitting – Garden State Parkway Shoulder Widening/Reconstruction, MP 83.6 to MP 99.5 |
Greenman-Pedersen, Inc. |
$4,850,000.00 |
| A3178 |
On-Call Environmental Engineering Consultants – Soil and Groundwater Remedial Investigations, Remedial Design and Compliance Monitoring at Various locations along the Turnpike and Parkway Roadways |
Hatch Mott MacDonald |
$400,000.00 |
| A3179 |
On-Call Environmental Engineering Consultants – Soil and Groundwater Remedial Investigations, Remedial Design and Compliance Monitoring at Various locations along the Turnpike and Parkway Roadways |
Dewberry-Goodkind, Inc. |
$400,000.00 |
| P3180 |
Supervision of Construction Services for Contract No. P200.096, GSP Interim Shoulder Repair & Miscellaneous Safety Improvements, MP 89.7 to MP 96.1 |
Dewberry-Goodkind, Inc. |
$420,000.00 |
| T3181 |
Supervision of Construction Services for Contract No. T100.048, TPK Bridge No. N2.0, Interim Catwalk Safety Improvements; and Contract No. T100.095, Interim Zone Painting, Str. No. N2.01, Casciano Memorial Newark Bay Bridge |
HAKS Engineers, P.C. |
$798,000.00 |
» Back to Top
OCTOBER AWARDS
| OPS NO. |
PROJECT DESCRIPTION |
CONSULTANT |
AMOUNT |
| A3189 |
On-Call General Environmental Consulting Services |
The RBA Group |
$750,000.00 |
| A3190 |
On-Call General Environmental Consulting Services |
Langan Engineering & Environmental |
$750,000.00 |
| T3085 |
Design Services for Contract No. T100.034, TPK Bridge Deck Reconstruction, Miscellaneous Structural, Roadway and Lighting Improvements, NBHCE, MP N0.00 to MP N3.00 |
URS Corporation |
$3,350,000.00 |
| T3182 |
Operation, Maintenance & Compliance Monitoring of Remediation Systems; Remedial Investigation and Remedial |
Hatch Mott MacDonald |
$500,000.00 |
» Back to Top
JULY AWARDS
| OPS NO. |
PROJECT DESCRIPTION |
CONSULTANT |
AMOUNT |
| P3135 |
Supervision of Construction Services for Contract No. P700.047, Underground Storage Tank Upgrade/Removal at Various GSP Facilities |
Hatch Mott MacDonald |
$330,000.00 |
| P3137 |
Supervision of Construction Services for Contract No. P300.043, Improvements to GSP Interchange 67 |
Stone & Webster, Inc. |
$2,150,000.00 |
| T3167 |
Supervision of Construction Services for Contract No. T300.064, Ramp NWC Improvements at Interchange 18W, Roadway Widening, Grading, Paving and Structures |
The RBA Group |
$1,042,600.00 |
| P3175 |
Preliminary Design & Environmental Permitting – Garden State Parkway Shoulder Widening/Reconstruction, MP 83.6 to MP 99.5 |
Greenman-Pedersen, Inc. |
$4,850,000.00 |
| A3178 |
On-Call Environmental Engineering Consultants – Soil and Groundwater Remedial Investigations, Remedial Design and Compliance Monitoring at Various locations along the Turnpike and Parkway Roadways |
Hatch Mott MacDonald |
$400,000.00 |
| A3179 |
On-Call Environmental Engineering Consultants – Soil and Groundwater Remedial Investigations, Remedial Design and Compliance Monitoring at Various locations along the Turnpike and Parkway Roadways |
Dewberry-Goodkind, Inc. |
$400,000.00 |
| P3180 |
Supervision of Construction Services for Contract No. P200.096, GSP Interim Shoulder Repair & Miscellaneous Safety Improvements, MP 89.7 to MP 96.1 |
Dewberry-Goodkind, Inc. |
$420,000.00 |
| T3181 |
Supervision of Construction Services for Contract No. T100.048, TPK Bridge No. N2.0, Interim Catwalk Safety Improvements; and Contract No. T100.095, Interim Zone Painting, Str. No. N2.01, Casciano Memorial Newark Bay Bridge |
HAKS Engineers, P.C. |
$798,000.00 |
» Back to Top
MAY AWARDS
| OPS NO. |
PROJECT DESCRIPTION |
CONSULTANT |
AMOUNT |
| P3099 |
Supervision of Construction Services for Contract No. P200.021, Widening of the GSP at Interchange 98 |
Boswell Engineering |
$695,000.00 |
| P3176 |
Engineering Services for 2008 New Jersey Turnpike Authority Bridge Inspection Program, Inspection of 16 Microwave |
Churchill Consulting Engineers |
$178,000.00 |
| P3157 |
Supervision of Construction Services for Contract No. P100.074, Southern Bridge Deck Repairs and Resurfacing |
PB Americas, Inc. |
$661,000.00 |
» Back to Top
APRIL AWARDS
| OPS NO. |
PROJECT DESCRIPTION |
CONSULTANT |
AMOUNT |
| T3173 |
Constructability Consultant for the New Jersey Turnpike Interchange 6 to 9 Widening Program |
DMJM Harris/GPI/PB, A Joint Venture |
$155,000.00 |
| T3169 |
Supervision of Construction Services for Contract No.T200.085, Resurfacing, Turnpike MP 74 to MP 122 |
Kupper Associates |
$410,000.00 |
| A3174 |
On-Call Architectural Services |
Yezzi Associates, LLC |
$500,000.00 |
» Back to Top
FEBRUAY AWARDS
| OPS NO. |
PROJECT DESCRIPTION |
CONSULTANT |
AMOUNT |
| P3165 |
Supervision of Construction Services for Contract No.P200.082, Pavement Rehabilitation & Miscellaneous Repairs, GSP MP 104 to MP 116 SBO |
Kupper Associates. |
$420,000.00 |
| P3166 |
Supervision of Construction Services for Contract No. P200.083, Pavement Rehabilitation & Miscellaneous Repairs, GSP |
KS Engineers, P.C. |
$350,000.00 |
| T3172 |
2008 Turnpike Bridge Inspection Program, Part C |
LS Engineering Associates Corporation |
$500,000.00 |
» Back to Top
JANUARY AWARDS
| OPS NO. |
PROJECT DESCRIPTION |
CONSULTANT |
AMOUNT |
| T3148 |
Operation, Maintenance and Compliance Monitoring, Turnpike Service Areas 1S (Clara Barton) and 1N (John Fenwick) |
Hatch Mott MacDonald |
$588,000.00 |
| P3156 |
Supervision of Construction Services for Contract No.P100.053, GSP Central Bridge Deck Repairs and Resurfacing, MP 104 to MP 127 |
Kupper Associates |
$619,000.00 |
| P3158 |
Supervision of Construction Services for Contract No., P100.062, Miscellaneous Structural Repairs, GSP MP 0 to MP 172 |
Urbitran Associates, Inc. |
$465,000.00 |
| P3159 |
Supervision of Construction Services for Contract No. P100.007, Parkway Northern Bridge Deck Repairs and Resurfacing |
Greenman-Pedersen, Inc. |
$635,000.00 |
| T3161 |
Supervision of Construction Services for Contract No. T100.055, TPK Southern Bridge Deck Repairs and Resurfacing, MP 0 to MP 83 and the PHMTE |
Jacobs Edwards & Kelcey |
$665,000.00 |
| T3162 |
Operation, Maintenance and Monitoring of Remediation Systems at Thomas Edison Service Area, 10S |
Dresdner Robin Environmental Management, Inc. |
$329,000.00 |
| T3163 |
Design Services for Contract No. T100.089, TPK Miscellaneous Structural Repairs, MP 0 to MP 122, PHMTE and NBHCE |
TransSystems |
$450,000.00 |
| P3164 |
Design Services for Contract No. P100.090, Miscellaneous Structural Repairs, GSP MP 0.0 to MP 172.0 |
IH Engineers, P.C. |
$414,000.00 |
| T3171 |
2008 NJTA Bridge Inspection Program, Turnpike Main Bridge Inspection, Part B |
Chas. H. Sells, Inc. |
$862,800.00 |