FOR IMMEDIATE RELEASE
May 31, 2017

Contact: Caryn Shinske (609) 984-1795
Lawrence Hajna (609) 984-1795
Bob Considine (609) 292-2994

DEP, U.S. ARMY CORPS OF ENGINEERS BEGIN NORTHERN OCEAN COUNTY BEACH
REPLENISHMENT WORK AT ORTLEY BEACH IN TOMS RIVER

BEACH DEVASTATED DURING SUPSERSTORM SANDY PART OF $128 MILLION SHORE PROTECTION PROJECT TO BUILD DUNES,
BEACHES IN REGION

(17/P53) TRENTON – Sand pumping and other work to better protect exposed beaches in the Ortley Beach section of Toms River is under way, marking the start of the long-awaited northern Ocean County beach replenishment project to protect coastal communities vulnerable to significant storm damage, DEP Commissioner Bob Martin announced today.

Contractor Weeks Marine of Cranford began pumping sand today in Ortley Beach, which sustained catastrophic damage during Superstorm Sandy in October 2012. The work is part of a $128 million project by DEP, in partnership with the U.S. Army Corps of Engineers, to build beaches and dunes in northern Ocean County.

“The Christie Administration is pleased that this critical project has begun because it will protect vulnerable beaches along our coast by developing a statewide system of engineered beaches,” DEP Commissioner Bob Martin said. “After seeing the devastation that Superstorm Sandy caused in Ortley Beach and other communities, projects such as these are vitally important for protecting lives and property, and for improving flood resiliency.”

Ortley Beach will receive approximately 267,000 cubic yards of sand that will create an approximate 125-foot-wide beach. Dredges will pump sand for approximately two weeks before moving to the Absecon Island beach and dune construction project. Work in northern Ocean County will resume in late summer, starting in Mantoloking.

The Army Corps of Engineers’ updated schedule for work at other northern Ocean County beaches is as follows. The schedule is subject to change due to weather, mechanical issues and if contract options are awarded:

  • Mantoloking: Mid-August to October 2017
  • Seaside Heights: October to November 2017
  • Ortley Beach (Completion): November to December 2017
  • Seaside Park: December 2017 to January 2018
  • Brick: Winter 2018
  • Normandy Beach (Toms River): Winter 2018
  • Lavallette: Spring 2018

Weeks Marine will work in 1,000-foot-wide sections of beaches at a time to reduce impacts to residents and visitors. The company will use multiple-suction hopper dredges, which are ships that pull up large volumes of sand from offshore before maneuvering closer to the beach in order to pump sand onto the beach. The contractor also will use a cutter-head dredge, which is a large barge that sits offshore and pumps sand continuously onto the beach via a pipeline.

"This represents one of the largest beachfill contracts in the history of the United States Army Corps of Engineers," said U.S. Army Corps of Engineers' Philadelphia District Commander Lt. Col. Michael Bliss. "The engineered dune and berm system will serve the vital purposes of reducing risk and helping to protect people and property."

“The Township is thrilled to see this critically important, long-overdue project finally moving forward and we thank DEP Commissioner Bob Martin for his support and cooperation throughout this process,” Toms River Mayor Thomas F. Kelaher said. “Toms River and Ortley Beach were hit particularly hard by Superstorm Sandy, losing more than $2 billion in ratables from the storm.  The Army Corps of Engineers project is one that the Township Governing Body demanded, and now we will have an engineered beach to prevent flooding. Once completed, the project will provide long term stability and peace of mind to all of the residents on the barrier island and the mainland.”

Engineered beaches and dunes absorb and reduce the impacts of storm surge while helping to protect lives, property and infrastructure. Northern Ocean County’s Barnegat Peninsula was hit especially hard when Superstorm Sandy slammed the state. 

The northern Ocean County project entails 11 million cubic yards of sand covering some 14 miles of coastline along the Barnegat Peninsula, protecting the communities of Point Pleasant Beach, Bay Head, Mantoloking, Brick, Toms River, Lavallette, Seaside Heights, Seaside Park and Berkeley Township.

For most of this project area, dunes will be built 22 feet above mean sea level. Beaches will be constructed from 100 feet to 300 feet wide and 8.5 feet above mean sea level. The project area will receive periodic replenishment projects over the course of 50 years to replace sand lost through normal erosion.

The federal government will pay for 65 percent of the project using money approved under the 2013 Disaster Relief Appropriations Act, which funds projects that Congress had previously authorized but had not been completed by the time Sandy hit. New Jersey will pay for 35 percent of the project from the state’s Shore Protection Fund.

To learn more about the Northern Ocean County project,
visit: www.nap.usace.army.mil/Missions/Civil-Works/Manasquan-Inlet-to-Barnegat-Inlet/

For more information on post-Sandy coastal projects in New Jersey,
visit: www.nj.gov/dep/shoreprotection/projects.htm 

###

 

News Releases: DEP News Home | Archives
Department: NJDEP Home | About DEP | Index by Topic | Programs/Units | DEP Online
Statewide: NJ Home | Services A to Z | Departments/Agencies | FAQs

Copyright © State of New Jersey, 1996-2024

Last Updated: May 31, 2017