I-95/295 Signing Redesignation Project Overview

Schedule


Anticipated Construction Timeline Key Work Primary Responsible Party
Phase 1

January – March 2018
Replacing signs in New Jersey starting at existing I-95 interchange 8/Princeton Pike and moving west toward the Delaware River NJDOT
Phase 2

March - April 2018
Replacing signs on both sides of the Delaware River within the Scudders Fall Bridge project limits (existing I-95 Exit 1 in New Jersey and Exits 51 and 49 in Pennsylvania).

DRJTBC/ PennDOT/PTC

Phase 3

April – August 2018
Replacing signs at the remaining interchanges through the new interchange in Bristol, PA.

PTC/PennDOT/ NJTA


 
Go to NJDOT home page Contact Us | Privacy Notice | Legal Statement | Accessibility Statement  Go to State of New Jersey home page
  department: home | about | NJ commuter | in the works | business | engineering | freight, air & water | capital | community | data | links | index
  statewide: NJ Home | about NJ | business | government | state services A to Z | departments

  Copyright © State of New Jersey, 2002-2018
  Department of Transportation
  P.O. Box 600
  Trenton, NJ 08625-0600
OPRA - open public records act

  Last Updated:  December 14, 2017