This portion of the project will provide for the construction of the river piers and fender system for a new vertical lift bridge over the Hackensack River. The new bridge will be located approximately 200 feet north of the existing bridge. Construction will also include Pier 1E, 1W and 2W and the pier protection system on each side of the channel as well as a dolphin in front of Pier 2W. This system consists of 73-eight foot diameter drilled shafts that are anchored into rock. All the piers and the cap of the pier protection system are reinforced concrete. The first contract is under construction and is scheduled for completion in Fall 2013.
Construction of off-line portions of the new bridge over the Hackensack River on the Jersey City side will be done in Contract 2. The new vertical lift span will be constructed under Contract 3. During this contract there will be minimal traffic impacts as this portion of the bridge and ramps are off the existing alignment. This contract includes:
This contract also includes various utility relocations to accomodate the new bridge and roadway alignment.
This part of the project will provide for the new vertical lift span over the Hackensack River. The new bridge is being constructed approximately 200 feet north of the existing bridge. This contract includes the construction of the lift span towers on the piers constructed in Contract 1. The lift span, counterweight, elevator and all mechanical and electrical systems will be completed so the span will be fully operational at the completion of the contract. The Control House and Machinery House are included in the lift span construction. The work tentatively covered under Contract 3 includes:
Construction of the final bridge and approach roadway segments of the new veritical lift bridge over the Hackensack River and the improvements to the interchange at Fish House Road will be completed. New connection ramps to Newark Avenue and St. Paul's Avenue will be provided along with the demolition of the existing Wittpenn Bridge. This contract includes:
|
||||||
|
| department: home | about | NJ commuter | in the works | business | engineering | freight, air & water | capital | community | data | links | index | ||
| statewide: NJ Home | about NJ | business | government | state services A to Z | departments |
||
| Copyright ©
State of New Jersey, 2002-2013 Department of Transportation P.O. Box 600 Trenton, NJ 08625-0600 |
|
|
Last Updated: June 11, 2012 |
||