Question and Answer For Current Technical Proposals

E-mail question(s) to the attention: Manager of Professional Services, Procurement. Specify "TP #281 question" in subject line.
Questions will be accepted up to question cut-off date noted in the technical proposal.

Technical Proposal
TP-288
Part 5 of the Instructions for Completing Forms notes that a Critical Path Model is required with the TP submission, while Part 5-Project Approach, Section 11, notes that a Critical Path Model is not required. Please clarify.
Section 11 should be NR.
If a firm is submitting a proposal as a prime for TP-288, can it also serve as a subconsultant on another team?
Yes, a prime can also serve as a sub
Although it is not stated to include, can you confirm that resumes are not required for support staff?
I confirm that since only the Team Leader/Key Staff will be rated for each task, resumes for staff that supports the Team Leader should not be submitted.
Can the organizational chart be submitted in 11”x17” landscape format?
Yes.